Sponsored by AEP Texas

Fire sprinkler mains placed at Victoria West school

Locker bases were installed at Victoria East High School last week. Locker bases were installed at Victoria East High School last week.
  • Print
  • Post a Comment
  • Favorite

Construction continues for the three Victoria school district campuses. All schools are scheduled to open in fall 2010.

Victoria West High School and Harold Cade Middle School

Continued roof gravel are A and B. 95 percent complete. Roof dry-in complete, metal coping at parapet walls 85 percent complete

Continued framing and lath for plaster ceilings are H and north side of entry canopy

Formed and poured remaining locker bases in boys' athletics- area H

Installed wood blocking at clerestory window openings at high school

Installed split faced masonry to stair No. 1 and 4 in high school

Drywall framing clerestory walls and north side administration extension wall

Fire sprinkler mains on second floor 99 percent complete, continued third floor mains at high school

Electrical rough-in on second floor, piping rough in auditorium, starting pulling main electrical feeds from transformer to main switch gear

Installed third floor ductwork area A, continued chilled water piping to boilers

Started installing acid waste piping, second floor domestic water, tested roof drain piping for CPR 12r

Tape/float on second floor sheet rock top out 99 percent complete, started third floor

Installed remaining windows on south side area B

Installed z-furring strips for metal panels at west side entry to gym area G in high school

Tape, float and paint area A and B on first and second floor

Continued installing ceramic tile in area A and B restrooms on second floor in middle school

Completed mechanical yard masonry walls in middle school

Installed ceiling grid and light fixtures in middle school

Installed walk-in coolers at middle school

Continued installing millwork at middle school

Continued cold rolled framing to top of walls at exposed ceiling locations

Installed processed road base at service yard at 25 percent complete

Victoria East High School

Began installing metal wall panels, locker bases

Completed conduit boxes in area G

Installed interior CMU walls

Completed various CMU pinch list items

Began installing metal wall panels, roof in area E

Began installing plaster soffit at clear story, masonry at stair No. 3 and 4

Began installing windows in area B, C and D east wall.