School work update: Construction begins on auditorium at Victoria East

Construction workers work on the stairs at Harold Cade Middle School. Construction workers work on the stairs at Harold Cade Middle School.
  • Print
  • Post a Comment
  • Favorite

Construction continues for the three new campuses in Victoria. All three are scheduled to open in fall 2010.

Victoria West and middle school

Started ceramic tile in restrooms H143 and 144

Installed second coat of plaster north side entry canopy

Continued burnished block at star No. 1 and 3 at high school

Started wall panels on west side of gym, installed metal cap at mechanical yard at high school

Damp-proofing sloped soffit at exterior of clerestory

Drywall framing under clerestory in library, installed dens glass at stair No. 1 and north side administration exterior wall

Formed remaining areaways, poured steps to sound booth, poured floor hatches

Electrical rough-in on second floor, piping rough-in auditorium, continued pulling main electrical feeds from transformer to main switch gear

Continued installing third floor ductwork

Continued installing acid waste piping, second floor domestic water, and insulation ongoing

Started dirt work at mechanical yard at high school

Started framing under canopy for metal panels at cafeteria entrance

Installed curtain wall on second floor at west side of middle school

Tape, float, and paint are A and B on first and second floor 80 percent complete

Started tape and float area C

Ran electrical conduits to chillers at middle school

Installed ceiling grid and light fixtures at middle school

Painted ceilings and exposed beams at library at middle school

Continued installing millwork at middle school

Continued installing millwork at middle school

Continued cold rolled framing to top of walls at exposed ceiling locations

Canopies installed at south side area D at middle school

Continued ceramic tile in area H, D and E restrooms

Started second coat of plaster ceilings in area H

Continued burnished block at stars No. 2, 3, and 4 at high school

Installed wall panels between windows south side area B

Drywall framing under clerestory in library

Installed fan powered terminals on second floor of high school

Installed ductwork on second and third floor, installed chilled water and heating water mains on second and third floor

Electrical rough-in on second floor, piping rough-in auditorium

Started exhaust duct replacement area H at high school

Continued installing acid waste piping, second floor domestic water, and insulation ongoing

Continued dirt work at mechanical yard at high school

Started framing under canopy for metal panels at cafeteria entrance of middle school

Prepped and painted door frames in area D

Tape, float, and paint are A and B on first, second floors - 85 percent complete

Continued tape and float area C

Formed and poured sidewalks on north side of middle school

Continued installing millwork at middle school

Continued cold rolled framing to top of walls at exposed ceiling locations

Canopies installed at east side area D and C of middle school

Started installing exterior wall packs at middle school

Ceramic tile restroom floor tile at middle school

Victoria West High School

Completed sheetrock/ plaster ceilings, painted walls in area H

Completed locker bases in area H

Began installing plumbing fixtures in area H

Completed canopy in area H

Completed ductwork/HVAC equipment in area G

Completed HVAC piping in area G

Completed conduit boxes, wood blocking west wall in area G

Installed roofing in area G

Began installing prime/ paint gym walls/ ceiling in area G

Installed canopy east

Installed sheetrock walls at kitchen, interior CMU walls, and block fill CMU in area F

Installed MEP rough-in, plaster at entry in area F

Began installing central plant HVAC/boiler piping/venting

Began work on auditorium

Completed exterior storefront doors in area E

Began exterior storefront doors in area E

Installed metal wall panels, canopy, roofing in area E

Installed plaster soffit at clear story

Installed rough-in on second floor, third floor

Installed frame/sheath walls at stair No. 1

Began installing masonry stair No. 1

Installed windows in area A

Completed frame/sheath walls at stair No. 2

Completed masonry at stair No. 3, 4

Completed masonry at radius wall on first floor

Installed exterior brick at stair No. 3, 4

Installed frame/sheath exterior walls B side, exterior brick, windows in area B

Installed frame and rock elevator shaft wall, third floor walls, frame interior clear story walls

Installed Type 1 roofing on area A, B, C, D

Installed sendero punch list items, final grade areas H, G, F, E

Began installing marquee sign, sidewalks