School work update: Construction begins on auditorium at Victoria East
Print- •
- •
-
Post a Comment
- •
Favorite- •
Construction continues for the three new campuses in Victoria. All three are scheduled to open in fall 2010.
Victoria West and middle school
Started ceramic tile in restrooms H143 and 144
Installed second coat of plaster north side entry canopy
Continued burnished block at star No. 1 and 3 at high school
Started wall panels on west side of gym, installed metal cap at mechanical yard at high school
Damp-proofing sloped soffit at exterior of clerestory
Drywall framing under clerestory in library, installed dens glass at stair No. 1 and north side administration exterior wall
Formed remaining areaways, poured steps to sound booth, poured floor hatches
Electrical rough-in on second floor, piping rough-in auditorium, continued pulling main electrical feeds from transformer to main switch gear
Continued installing third floor ductwork
Continued installing acid waste piping, second floor domestic water, and insulation ongoing
Started dirt work at mechanical yard at high school
Started framing under canopy for metal panels at cafeteria entrance
Installed curtain wall on second floor at west side of middle school
Tape, float, and paint are A and B on first and second floor 80 percent complete
Started tape and float area C
Ran electrical conduits to chillers at middle school
Installed ceiling grid and light fixtures at middle school
Painted ceilings and exposed beams at library at middle school
Continued installing millwork at middle school
Continued installing millwork at middle school
Continued cold rolled framing to top of walls at exposed ceiling locations
Canopies installed at south side area D at middle school
Continued ceramic tile in area H, D and E restrooms
Started second coat of plaster ceilings in area H
Continued burnished block at stars No. 2, 3, and 4 at high school
Installed wall panels between windows south side area B
Drywall framing under clerestory in library
Installed fan powered terminals on second floor of high school
Installed ductwork on second and third floor, installed chilled water and heating water mains on second and third floor
Electrical rough-in on second floor, piping rough-in auditorium
Started exhaust duct replacement area H at high school
Continued installing acid waste piping, second floor domestic water, and insulation ongoing
Continued dirt work at mechanical yard at high school
Started framing under canopy for metal panels at cafeteria entrance of middle school
Prepped and painted door frames in area D
Tape, float, and paint are A and B on first, second floors - 85 percent complete
Continued tape and float area C
Formed and poured sidewalks on north side of middle school
Continued installing millwork at middle school
Continued cold rolled framing to top of walls at exposed ceiling locations
Canopies installed at east side area D and C of middle school
Started installing exterior wall packs at middle school
Ceramic tile restroom floor tile at middle school
Victoria West High School
Completed sheetrock/ plaster ceilings, painted walls in area H
Completed locker bases in area H
Began installing plumbing fixtures in area H
Completed canopy in area H
Completed ductwork/HVAC equipment in area G
Completed HVAC piping in area G
Completed conduit boxes, wood blocking west wall in area G
Installed roofing in area G
Began installing prime/ paint gym walls/ ceiling in area G
Installed canopy east
Installed sheetrock walls at kitchen, interior CMU walls, and block fill CMU in area F
Installed MEP rough-in, plaster at entry in area F
Began installing central plant HVAC/boiler piping/venting
Began work on auditorium
Completed exterior storefront doors in area E
Began exterior storefront doors in area E
Installed metal wall panels, canopy, roofing in area E
Installed plaster soffit at clear story
Installed rough-in on second floor, third floor
Installed frame/sheath walls at stair No. 1
Began installing masonry stair No. 1
Installed windows in area A
Completed frame/sheath walls at stair No. 2
Completed masonry at stair No. 3, 4
Completed masonry at radius wall on first floor
Installed exterior brick at stair No. 3, 4
Installed frame/sheath exterior walls B side, exterior brick, windows in area B
Installed frame and rock elevator shaft wall, third floor walls, frame interior clear story walls
Installed Type 1 roofing on area A, B, C, D
Installed sendero punch list items, final grade areas H, G, F, E
Began installing marquee sign, sidewalks
