Construction update: School work on schedule
Print- •
- •
-
Post a Comment
- •
Favorite- •
-
Report error
-
Thank you for your submission.Error report or correction
- Close
-
- •
Construction continues for Victoria school district two new high schools and new middle schools.
The three schools are set to open next August.
Victoria West and middle school
Completed installation of brick on high roof wall east side between areas D and C
Plumbing, and HVAC work ongoing at the high school
Starting split-faced CMU at radius wall at north and south entry, completed walls of area D restrooms, started servery CMU wall
Painted gym ceilings and walls, primed door frames area at high school
Completed squandrel beams in area E of the high school
Installed gravel on the auditorium roof. 95 percent complete
Continued fire sprinkler mains in areas C and D of the high school
Started installing aluminum windows in areas A and C. Is 75 percent complete
Roof drain piping on the third floor is 50 percent complete
Third floor drywall framing. 60 percent complete
Started installing duct straps and hangers in area E of high school auditorium
Installed dens glass at exterior walls of areas B and D. 95 percent complete
Installed steel for CPR No. 71 at entry doors for canopy supports
Continued plumbing and duct insulation for first and second floor areas A and B of the middle school
Continued framing plaster ceilings in the middle school dressing rooms and porches
Continued sheet rock and tape/float on the first and second floor of areas A and B of the middle school
Started pulling wire to all areas of the middle school
Plumbing top out area B 100 percent on the first and second floor. Area A is 98 percent complete of the middle school
Completed gravel on area A and B and 90 percent of area C of the middle school
Continued sidewalks in area D of the middle school
Victoria East High School
Started painting the walls and placing the windows of area H
Began installing conduit/boxes, and the exterior metal frame wall west of area G
Completed the structural steel detailing of area G
Completed the metal framing and exterior brick of columns at the entry of area F
Began work on frame/sheath at clear story of area A, B, C and D on first, second and third floors
Began work on frame/sheath of exterior walls C, D on third floor to parapet
Completed the repair light pole bases