VISD school construction nears finish line

Victoria West High School undergoes final procedures before opening up for the new school year.

Victoria West High School

Cleaning parking lots and striping

Installing first floor hardware

Started installing bleachers in both gyms

Installing added exit signs

Installing sound system in auditorium

Final plumbing inspection approval, received fire marshal on fire sprinkler system

Finished irrigation system and started planting trees

Cade Middle School

Working on punch list items all areas 90 percent complete

Miscellaneous electrical work for added scope all areas